College Park Duvall Field Renovation XX
line gif
Planning Assistance to Municipalities and Communities Program

College Park Duvall Field map
click to enlarge map
Goal:

To renovate Duvall Field

Objective(s):

Prepare a conceptual plan to address:

· Renovation of the concession stand
· Reconstruction of the picnic area
· Reconstruction of the amphitheater seating area
· Reconfiguration of the parking area and pedestrian access

Milestones:

Description
Due Date
1. Pre-planning (PAMC project request)
10/05/04
2. Planning Board Authorization/Initiation
12/09/04
3. Analyze Existing Facility Conditions
02/01/05
4. Conduct Community and Stakeholder Meetings
02/15/05
5. Prepare Conceptual Plan
03/22/05
6. Present Conceptual Plan to Community
8/05 - 9/05
7. Planning Board Backup
9/05 - 10/05
8. Planning Board Permission to Transmit 9/05 - 10/05
9. Project Transmittal to College Park 10/05

 

 

 



Budget:

Fiscal Year
Staffweeks
Professional Services
Other
FY05
Subtotal
ComPlanDiv
0
0
10
1


Status:
On August 24, a community meeting was held to review the concept plan and priority/phasing recommendations for the renovation of Duvall Field. Park Planning and Development staff will finalize the concept plan per the comments received at the community meeting. The city of College Park will proceed to secure funding and hire consultants to develop the engineering drawings and secure permits. In Fall 2005, permission to transmit this project to the city of College park will be requested of the Planning Board.

Staff:

Larry Hill , Supervisor
Eileen Nivera, Planner Coordinator, Park Planning and Development
.

Last update: 9/02/05

Top| Privacy Policy | Contact Us | Site Map