Planning staff is currently drafting the Preliminary Subregion 5 Master Plan and Sectional Map Amendment. The draft preliminary plan will be available to the public in February 2009. The planning staff will hold a subregion-wide informational meeting on the plan’s preliminary recommendations in early November.
More information on the date, time, and location of this meeting will be available on this website in the coming weeks.
Project Timeline
*Assemble background information and analyze existing conditions * Research demographic and economic conditions
* Map recent development activity
* Identify stakeholders
* Develop webpage
* Contract planning consultant team
* Begin community outreach
Spring-Summer
2007
Approval of Goals, Concepts, Guidelines and Public Participation Program
Fall
2007
Plan Formulation
Spring-Fall 2008
Preliminary Master Plan and SMA available for review
Winter 2009
Joint Public Hearing/Planning Board Adoption
Spring
2009
District Council Review Amendment Hearings (if needed) and Final Approval