The Transit District Development plan process of Prince George's County Planning Department is uniquely different because it is a legislated process determined by the Prince George’s County Council. The County’s legislation provides a flexible timeline for TDDP/TDOZ plans to be completed after plan initiation. The New Carrollton TDDP/TDOZ initiated during the winter of 2007. Once a plan is initiated, planning staff are required to meet certain milestones include community workshops, completion of a preliminary draft of the plan, and public hearings held by the Planning Board and County Council. With a plan initiation date in spring 2008, County Council will encourage M-NCPPC staff to complete the plan by late 2009.
| 1. Project Initiation | 09-10/07 |
| 2. Communitywide Forums | 10/07 - 04/08 |
| 3. Draft TDDP/TDOZ | 04/08 - 10/08 |
| 4. PB Permission to Print | 10/08 |
| 5. Public Release (60 days before PH) | 10/08 |
| 6. Joint Public Hearing | 01/09 |
| 7. Transmit TDDP/TDOZ to DC | 03/09 |
| 8. DC Work Session | 04/09 |
| 9. 2nd Joint Public Hearing on Amendments | 05/09 |
| 10. DC Work Session – Recommend Approval | 06/09 |
| 11. DC Approval of TDDP/TDOZ | 07/09
|