West Hyattsville Metro Transit-Oriented Development (TOD) Planning Study

PROJECT DESCRIPTION
PROJECT BOUNDARY MAP
BOUNDARY DESCRIPTION

 
PROJECT DESCRIPTION

The West Hyattsville Metro Transit-Oriented Development (TOD) Planning Study is a joint project of MDOT/Planning, the Governor's Office of Smart Growth, the City of Hyattsville, WMATA and the M-NCPPC Planning Department. This study was begun during the third quarter of FYO2 at the initiative of Councilman Shapiro and should be completed by the end of the calendar year. It will serve a "pilot" function for the Planning Department's county-wide strategic plan for TOD. The study will build upon the 1998 West Hyattsville approved TDDP for the TDOZ but will likely include more land area. MDOT shares the county's interest in the West Hyattsville Metro Station area and wishes in addition to explore the extent to which state-supported analysis and outreach can contribute to increases in TOD market value and TOD market interest. The Governor's Office of Smart Growth wishes to promote development activities that provide state-wide exemplars of smart growth and seeks through coordination to maximize the impact of state resources supporting smart growth. A team of planning and development consultants has been provided by MDOT. The TOD policy objectives of both the state and the county in the West Hyattsville area are as follows:

  • Identification of market-based TOD development scenarios.

  • Ability of existing TDOZ and other regulations to respond to market realities.

  • Community reaction to market-based TOD development scenarios.

  • Developer assessment of market-based TOD development scenarios.

  • Identification of funding/financial gaps to address through public-private partnerships.

  • Information about the marketability of TOD within Prince George's County.


BOUNDARY MAP

West Hyattsville Metro Transit-Oriented Development Planning Study Map
CLICK TO ENLARGE MAP


BOUNDARY DESCRIPTION

Properties generally within a one-half-mile radius of the West Hyattsville Metro Station are included within the TOD study area boundary.


PROJECT MILESTONE, SCHEDULE AND TIMELINE

TASK 1

GATHER BACKGROUND INFORMATION
6/02
TASK 2 ANALYZE POTENTIAL MARKET SUPPORT
6/02
TASK 3

CREATE THREE POTENTIAL DEVELOPMENT SCENARIOS

7/02
TASK 4 DEVELOPERS' FORUM
8/02
TASK 5 ECONOMIC ANALYSIS OF SCENARIOS
9/02
TASK 6 SELECT PREFERRED ALTERNATIVE
09/05/02
10/02
TASK 7 DETAILED ECONOMIC ANALYSIS
11/02
TASK 8 IDENTIFY NEXT STEPS
2/03

POST STUDY IMPLEMENTATION STEPS

Project Completed - The Final Consultant Report

3/03- 6/03

NEWS BRIEF

The final consultant report was reviewed by the County Executive staff at the Economic Development Cluster meeting in June. A briefing for the Mayor and City Council in Hyattsville is scheduled for July 14 at Hyattsville City Hall.


CONTACT INFORMATION

Bill Washburn, 301-952-3166, william.washburn@ppd.mncppc.org
Ragaei Abdelfattah, Project Facilitator, 301-952-4711; ragaei.abdelfattah@ppd.mncppc.org

Last update: 12/12/07