Field Irrigation Projects

Project Background/Description

M-NCPPC, Department of Parks and Recreation seeks to add sports field irrigation to five (5) existing field sites. Each site has differing existing conditions. The Park Planning and Development Division is working with one design consultant to design and permit these projects.

The five park sites are as follows:

  • Beltsville Community Center
  • Fairwood Park
  • Glenarden Community Center
  • Landover Hills Community Center
  • Sasscer Park

Status/Project Updates

Last Updated March 2022

To reduce the number of fields out of service at one time, the projects will occur in phases. The order that the fields will be completed is as follows:

  • Sasscer Park – Completed, April 2021.
  • Beltsville Community Center – Construction phase, projected completion October/November 2023.
  • Glenarden Community Center – Design and permitting phase, projected completion November 2023.
  • Landover Hills Park – Design and permitting phase, projected completion November 2023.
  • Fairwood Park – Design and permitting phase, projected completion November 2023.

Actual dates for the completion of the milestones are subject to change.